DCI delivered a complete gypsum board production line with an annual output of 10 million m² in Kyrgyzstan. The project was handled on a turnkey basis — engineering design, equipment manufacturing, shipping, on-site installation, commissioning and operator training — and the line is now in production.

As a gypsum board production line supplier working across Central Asia, DCI installed this line as part of the company's wider gypsum plant installation programme in the region.

Equipment Scope

●Mixer — compact structure, optimized stirring disc, reduced slurry residence time, foam added at the discharge port to cut foaming agent consumption

●Shaping machine — extruded moulding for vertical edges, flat surface and uniform thickness, with no edge leakage

●Dynamic foaming system — fixed and high-speed rotating grinder generate shear, friction and impact forces to produce fine, uniform bubbles; bubble diameter is adjustable

●Automatic paper supply and joint system — hydraulic paper roll, automatic joint machine and cross convey device; design speed 0–150 m/min, maximum paper roll weight 3 t

●Drying system — direct-combustion hot air stove, PLC-controlled dryer

●Gypsum board dunnage machine — saws waste board into strips for packing; adjustable strip width, dust-free

●Automatic board stack packing system — packs stacks in 4 or 6 faces by conveying and film winding

●Siemens PLC full-automatic control system

Technical Specifications

Parameter

Specification

Annual capacity

10 million m²/year

Production speed

20 m/min

Dryer layers

8

Heat

600 kcal

Board thickness

7 – 20 mm

Board width

1200 – 1220 mm

Board length

2400 – 3600 mm (adjustable)

Drying system

hot air stove drying system

Automation

full-automatic (Siemens PLC)

Quality standard

GB/T 9775-2008 and equivalent international standard

Board types

regular, moisture-resistant and fire-resistant

Fuel

natural gas, heavy oil, coal or diesel

Technical data are taken from DCI's standard configuration for the 10 million m²/year capacity class. Final configuration is confirmed against the customer's site conditions and raw material.

Heating System

The line uses a direct-combustion hot air stove with a built-in burner mounted inside the air duct and the fan outside it. Combustion is direct with no heat exchange device, giving gas use efficiency close to 100%. The stove wall is made of high-temperature stainless steel, and the stove adjustment ratio is above 1:10, allowing the same line to run different board thicknesses and line speeds.

Product and Value

The line produces paper-faced gypsum board for interior walls, ceilings and fire-rated partitions. By adjusting formulation and additives — including fiberglass for fire-resistant board and silicone oil for water-resistant board — the same line can switch between regular, moisture-resistant and fire-resistant board.

For the customer, local production replaces imported board and shortens supply lead times, while the 10 million m²/year capacity is sized to serve the domestic market.

Result

The line is in production and running at its rated output, operated by a locally trained team. DCI engineers remained on site through installation and commissioning, and the project carries a one-year warranty with remote support and spare parts supply.

Frequently Asked Questions

Q: What capacity was delivered for this project?

A: 10 million m² per year, based on 9.5 mm board thickness.

Q: What board sizes can the line produce?

A: Thickness 7 to 20 mm, width 1200 to 1220 mm and length 2400 to 3600 mm, adjustable.

Q: Who carried out the installation and commissioning?

A: DCI sent its own engineers to site. They completed mechanical installation, electrical commissioning and both cold and hot trial runs, and remained on site until the line reached its rated output and the local team could operate it independently.

Q: What standard does the board meet?

A: GB/T 9775-2008 and equivalent international standards.

Q: How long does installation and commissioning take on a project of this size?

A: Typically 4 to 6 months from equipment arrival, depending on site readiness and line size.

Call to Action

Planning a gypsum board plant or a capacity expansion? Tell us your target capacity, raw material type and available fuel — we will provide a tailored configuration and proposal.

Hengshui Decheng Machinery & Equipment Co., Ltd. (DCI) — Email: dci@chinagypsummachine.com | WhatsApp: +86 13930110827 / +86 18203235588 

| Web: www.dcimachine.com

HOT PRODUCTS

Processing Demand Survey

x